Container orchestration Representative engagement

Three major versions crossed, one workload restarted on purpose

Kubernetes — version upgrade programme

Client
Logistics technology · EU
Region
Single region, three availability zones
Scale
1 cluster · 96 nodes · 5 minor versions behind
Timeline
7 weeks, staged across three windows

Where they started

The cluster was five minor versions behind, which meant the supported upgrade path no longer existed in a single hop and several deprecated APIs were still in use.

The problem, precisely

A large share of manifests used removed APIs, and the team had no inventory of which workloads would break.

What we did

Ran a pre-upgrade scan to enumerate removed and deprecated API usage, converted manifests in Git before touching the cluster, then upgraded in three hops with a staging rehearsal for each.

Delivered

  • Removed-API inventory across all manifests, with conversion applied in Git
  • Add-on compatibility matrix checked against the target versions before starting
  • Three staged upgrades, each rehearsed on staging with the same manifests
  • Rollback plan per hop, exercised as a dry run rather than assumed
  • Version policy written down: never more than two minors behind

Technologies used

  • Cluster API
  • kubeadm
  • Pluto / kubent API scan
  • Argo CD
  • Velero
  • Prometheus + Alertmanager

Measured result

Every number below was measured and reported to the customer. Where we do not have a measured figure, the entry is a fact rather than a percentage — we would rather be precise than impressive.

  • 3 major hops completed in planned windows
  • 1 workload restarted deliberately, none unexpectedly
  • 0 rollbacks required
  • ≤ 2 minor versions behind, now a written policy
The reusable part

Convert manifests in Git before you touch the cluster. Almost every "the upgrade broke it" incident is a removed API that was sitting in a repository the whole time.