Virtualisation & VDI Representative engagement

Four nodes to eleven, with the storage rebalancing planned rather than survived

Hyperconverged cluster (Proxmox VE + Ceph / Harvester)

Client
Regional healthcare group · US
Region
Two sites, clinical systems
Scale
4 → 11 nodes · 260TB raw · 480 VMs and workloads
Timeline
9 weeks, three expansion steps
Service line
Virtualization & HCI

Where they started

A four-node cluster was running at 82% capacity with no headroom for a failover, and the last expansion attempt had caused a visible performance dip during the day.

The problem, precisely

Adding nodes rebalances data across the whole cluster, and the previous attempt did it under peak load with no throttling.

What we did

Modelled the CRUSH redistribution before touching hardware, then added nodes one at a time with backfill throttled to a measured ceiling and monitoring on client latency rather than cluster health alone.

Delivered

  • Growth model: capacity, failure-domain and rebalance-time forecast to 20 nodes
  • Three expansion steps, each with backfill throttled and latency watched
  • Failure-domain review — the previous layout had two nodes sharing a PDU
  • Client-visible latency budget written down and monitored during every change
  • Spare-node plan so a failure during expansion does not become an outage

Technologies used

  • Proxmox VE 8
  • Ceph (Reef) · backfill throttling
  • Ceph MDS
  • Corosync
  • Prometheus + Grafana
  • NVMe WAL/DB devices

Measured result

Every number below was measured and reported to the customer. Where we do not have a measured figure, the entry is a fact rather than a percentage — we would rather be precise than impressive.

  • 82% → 54% cluster utilisation after expansion
  • 0 user-visible incidents during rebalancing
  • 2 nodes found sharing a single power feed
  • 1 failover now survivable at full production load
The reusable part

Rebalancing is a scheduling problem, not a hardware problem. Throttle backfill against client latency and expansion stops being a maintenance-window event.